沈慧, 迟世春. Excavation Simulation and Numerical Analysis of Earthquake Response of Shield Tunnel[J]. 2007, (3): 284-289.DOI:
Excavation Simulation and Numerical Analysis of Earthquake Response of Shield Tunnel
摘要
由于盾构隧道掘进的特殊施工工艺
使开挖模拟的数值计算存在着诸多难以量化的因素。采用应力释放法模拟盾构隧道的开挖
在衬砌和土体之间设置等代层单元模拟盾构施工的影响
求得竣工期的应力场和位移场。在静力计算基础上运用动力有限元时程分析法
采用粘性人工边界条件
分析了隧道衬砌在地震过程中的最大响应。其结果和规律可为一般的盾构隧道地震反应分析提供借鉴。
Abstract
Because of the special construction process of shield tunnel
there are several factors difficult to estimate in the simulation of excavation.In this article
based on stress-releasing method
setting equivalent circle element between soil and lining to simulate the influence of shield tunnel construction
the stress and displacement distribution are determined.Furthermore
time history analysis of 3D dynamic nonlinear FEM with viscous boundary is adopted to research the earthquake response of lining.The maximum response of the lining is obtained.The paper reaches some beneficial rules and conclusions
which can provide reference and argument for seismic analysis of some general shield tunnels.