four tunnel-landslide parallel system model tests are conducted to study the time effect and deformation failure mode considering the interaction between tunnel and landslide under different conditions. The results show that: (1) Landslide thrust in parallel system of tunnel-landslide produces a critical state of stress in the sliding body. This critical state is in a transitional state of tension and compression stresses
with a time-varying process
that is
the time effect. (2) The bridge-connected pile foundation supporting structure can accelerate the time effect of critical stress-transient state
compared to the unsupported structure. (3) The landslide thrust in the landslide body firstly leads the soil near the sliding zone to reach the critical transitional state of stress; this critical state gradually moves from the trailing edge of the landslide body to the front edge. The relationship between the time and strain of each point will show different "S"-shaped curve characteristics. For the entire sliding body
the curve of time and strain at each point on the sliding surface presents different linear features at different moments. (4) Compared with the unsupported structure
the bridge-connected pile foundation supporting structure will delay the destruction of the tunnel model
so that the failure fracture extends toward the interior of the bedrock and the effect is remarkable. However
the overall damage of the tunnel model is within the bedrock.
关键词
Keywords
references
王建锋.两类经典滑坡发生时间预报模型的理论分析[J].地质力学学报,2004,10(1):42-52. Wang J F.A theoretical analysis of two types of classic landslide forecasting model [J].Journal of Geomechanics,2004,10(1):42-52.(in Chinese)
Kumar A,Asthana A,Priyanka R S,et al.Assessment of landslide hazards induced by extreme rainfall event in Jammu and Kashmir Himalaya,northwest India[J].Geomorphology,2017,284(5):72-87.
Bischetti G B,Chiaradia E A,D’agostino V,et al.Quantifying the effect of brush layering on slope stability[J].Ecological Engineering,2010,36(3):258-264.
卢应发,黄学斌,刘德富.推移式滑坡渐进破坏机制及稳定性分析[J].岩石力学与工程学报,2016,35(2):333-345. Lu Y F,Huang X B,Liu D F.Analysis of progressive failure mechanism and stability of sliding landslide [J].Chinese Journal of Rock Mechanics and Engineering,2016,35(2):333-345.(in Chinese)
段钊,李文可,王启耀.泾河下游台塬区黄土滑坡类型与时空分布规律[J].西安科技大学学报,2015,35(3):369-375. Duan Zh,Li W K,Wang Q Y.Distributions of loess landslides and their spatio-temporal distribution in the lower reaches of jinghe river [J].Journal of Xi’an University of Science and Technology,2015,35(3):369-375.(in Chinese)
牌立芳,赵金,吴红刚,等.刷方减重下隧道-滑坡平行体系变形演化试验研究[J].防灾减灾工程学报,2019,39(5):842-850. Pai L F,Zhao J,Wu H G,et al.Experimental study on deformation evolution of tunnel landslide parallel system under brush weight reduction [J].Journal of Disaster Prevention and Mitigation Engineering,2019,39(5):842-850.(in Chinese)
牌立芳,赖天文,吴红刚.陆路交通隧道-滑坡平行体系模型建立与试验验证[J].铁道建筑,2018,58(12):64-68. Pai L F,Lai T W,Wu H G.Establishment and experimental verification of parallel system model of land traffic tunnel landslide [J].Railway architecture,2018,58(12):64-68.(in Chinese)
魏林森,丁宏伟,王婷,等.降水对陇西黄土滑坡的诱发作用及时空影响分析[J].冰川冻土,2017,39(3):609-615. Wei L S,Ding H W,Wang T,et al.Effect of precipitation on loess landslide in longxi and its temporal and spatial analysis [J].Journal of Glaciology and Geocryology,2017,39(3):609-615.(in Chinese)
王建勇.滑体蠕动工况下抗滑桩的受力分析[D].重庆:重庆大学,2012. Wang J Y.Analysis of anti-slide piles under creep movement [D].Chongqing:Chongqing University,2012.(in Chinese)
娄海成.浅埋偏压大断面隧道围岩变形与支护受力研究[D].北京:北京交通大学,2015. Lou H Ch.Research on deformation and supporting forces of surrounding rock in shallow-buried large-section tunnel with bias pressure [D].Beijing:Beijing Jiaotong University,2015.(in Chinese)
Hasan M,Mandal B P.Tunneling time in space fractional quantum mechanics[J].Physics Letters A,2017,382(12):248-252.
Paraskevopoulou C,Diederichs M.Analysis of time-dependent deformation in tunnels using the Convergence-Confinement Method[J].Tunnelling and Underground Space Technology,2018,71(6):62-80.