何理,钟冬望,马建军,柯松林,宋琨,操鹏.钢筋砼支撑梁爆破拆除新技术及应用∗[J].防灾减灾工程学报,2020,(2):189-195
HE Li. New Blasting Demolition Technology and Its Application in Reinforced Concrete Support Beam Engineering[J]. 2020, (2): 189-195.
复杂环境下深基坑钢筋混凝土支撑梁的安全、高效拆除是城市建设过程中极为关键的环节。基于箍筋对支撑梁侧向约束作用机制的理论分析,揭示解除箍筋侧向约束效应前后梁内砼单元应力状态的演变规律及对支撑梁爆破效果的影响,并研发新的支撑梁线性切割预处理方法、布孔方法及其毫秒延时起爆网路,形成较为系统的支撑梁爆破拆除技术。工程应用结果表明,支撑梁线性切割预处理方法可显著增强拆除效果;多向协同布孔法可改善爆炸能量耦合状态,减小爆破飞石危害;基于爆破网路连接单元的毫秒延时起爆网路可有效控制振动强度,提高网路可靠性。
Safe and efficient demolition of reinforced concrete support beam in deep foundation pit under complex environment is a key point in the process of urban construction. On the basis of theoretical analysis on lateral restraint mechanism of stirrups
the evolution law for the stress state of the concrete element and the blasting effect of the supporting beam is revealed before and after the remove of the lateral restraint effect of the stirrup. The methods for stirrup cutting
shothole arrangement and millisecond delay initiation network are developed. A comparatively systematic technology on blasting demolition of support beams is formed. The result of engineering application shows that
the blasting demolition effect can be significantly enhanced by the linear cutting pretreatment method. The coupling state of explosion energy can be improved and the hazard of blasting flying rocks can be reduced by the method of multi-directional synergy arrangement of shotholes. The vibration intensity can be effectively controlled and the network reliability can be improved by the millisecond delay detonating network based on the blasting network connection unit.
温尊礼,顾月兵,韩文红.基坑围护钢筋混凝土支撑精确爆破拆除[J].探矿工程,2015,42(3):80-84. Wen Z L,Gu Y B,Han W H.Accurate blasting demolition of reinforced concrete support for foundation pit enclosure[J].Exploration Engineering,2015,42(3):80-84.(in Chinese)
刘伟,董超,徐岗,等.临地铁超深基坑复杂混凝土内支撑拆除施工技术[J].施工技术,2017(6):8-11. Liu W,Dong Ch,Xu G.Demolition construction of the complex concrete internal bracing in deep Foundation excavation adjacent to the subway[J].Construction Technology,2017(6):8-11.(in Chinese)
叶建军,程大春,明军.基坑钢筋混凝土临时支撑梁绿色拆除爆破技术[J].爆破,2017,34(1):101-107. Ye J J,Cheng D Ch,Ming J.Green explosive demolition of temporary reinforced concrete pit-supporting beams[J].Blasting,2017,34(1):101-107.(in Chinese)
杜宗,杜华彬,段义明,等.城市核心地段钢筋混凝土内支撑爆破降尘措施[J].爆破,2016,33(3):132-135. Du Z,Du H B,Duan Y M,et al.Dust-reduction measures of explosive demolition of reinforced concrete inner supporting in urban core area[J].Blasting,2016,33(3):132-135.(in Chinese)
杨建军,黄磊.全覆盖条件下城市基坑支撑梁爆破拆除[J].爆破,2015,32(4):99-102,117. Yang J J,Huang L.Explosive demolition of city foundation pit support beam under full covering[J].Blasting,2015,32(4):99-102,117.(in Chinese)
张兆龙.复杂环境下基坑支撑梁爆破拆除[J].爆破,2015,32(4):94-98. Zhang Zh L.Explosive demolition of foundation pit support beams under complex environment[J].Blasting,2015,32(4):94-98.(in Chinese)
何理,钟冬望,李琳娜,等.岩体爆破综合实验研究系统及其应用[J].矿冶工程,2017,37(2):36-35,49. He L,Zhong D W,Li L N,et al.A comprehensive experimental research system for rock blasting and its application[J].Mining and Metallurgical Engineering,2017,37(2):36-35,49.(in Chinese)
陈三定.深基坑支撑爆破拆除对周围建筑物稳定性的影响研究[D].合肥:安徽理工大学,2009. Chen S D.Study on the impact of the stability of surrounding buildings under deep foundation support basting[D].Hefei:Anhui University of Science and Technology,2009.(in Chinese)
赵坤,蒋昭镳.预埋炮孔法在钢筋混凝土支撑爆破拆除中的应用研究[J].爆破,2005,22(2):82-83,99. Zhao K,Jiang Zh B.Application of blasting demolition of shot preplugged hole in the reinforced concrete braces[J].Blasting,2005,22(2):82-83,99.(in Chinese)
何理,钟冬望,操鹏,等.多向协同布孔法爆破拆除深基坑支撑梁的应用[J].工程爆破,2017,23(4):44-47,53. He L,Zhong D W,Cao P,et al.Application of blast demolition deep foundation pit support beam of multi-directional synergy arrangement of blasthole[J].Engineering Blasting,2017,23(4):44-47,53.(in Chinese)
钟冬望,何理,李琳娜,等.一种多曲率换向耦合布孔的基坑内钢筋混凝土支撑梁:中国,ZL201620538910.X[P].2016-10-26. Zhong D W,He L,Li L N,et al.A reinforced concrete supporting beam in a foundation pit with multi directional synergistic blast holes:China,ZL201620538910.X[P].2016-10-26.(in Chinese)
钟冬望,操鹏,李琳娜,等.一种基坑内钢筋混凝土支撑梁的爆破拆除方法:中国,ZL201610393413.X[P].2016-10-26. Zhong D W,Cao P,Li L N,et al.A blasting demolition method of reinforced concrete supporting beam in foundation pit:China,ZL201610393413.X[P].2016-10-26.(in Chinese)
叶建军,程大春,舒大强,等.钢筋混凝土杆件轴向预埋孔绿色拆除爆破技术[J].科学技术与工程,2017,17(10):151-157. Ye J J,Chen D Ch,Shu D Q,et al.Green blasting technology for demolition of reinforced concrete bars by using pre-buried axial pipes as blast holes[J].Science Technology and Engineering,2017,17(10):151-157.(in Chinese)
Sheikh S A,Uzumeri S M.Analytical model for concrete confinement in tied columns [J].Journal of the Structural Division,ASCE,1982,108(12):2 703-2 722.
史庆轩,王南,田园,等.高强箍筋约束高强混凝土轴心受压应力-应变全曲线研究[J].建筑结构学报,2013,34(4):144-151. Shi Q X,Wang N,Tian Y,et al.Study on stress-strain relationship of high-strength concrete confined with high-strength stirrups under axial compression[J].Journal of Building Structures,2013,34(4):144-151.(in Chinese)
钟冬望,涂圣武,李琳娜,等.一种基于爆破拆除预处理的基坑内钢筋混凝土支撑梁:中国,ZL201620537861.8[P].2016-11-16. Zhong D W,Tu Sh W,Li L N,et al.A reinforced concrete support beam in foundation pit based on blasting pretreatment:China,ZL201620537861.8[P].2016-11-16.(in Chinese)
何理,钟冬望,李琳娜,等.布孔方式对支撑梁爆破拆除的影响机制[J].爆破,2018,35(3):85-91,119. He L,Zhong D W,Li L N,et al.Influence mechanism of blasthole arrangement on explosive demolition of support beam[J].Blasting,2018,35(3):85-91,119.(in Chinese)
邓兰艳,彭文,周谢萍,等.深基坑桁架式钢混内支撑梁的微差爆破拆除施工技术[J].建筑施工,2014(11):1 217-1 218. Deng L Y,Peng W,Zhou X P,et al.Construction technology of differential blasting demolition of truss type steel-concrete support beams in deep foundation pit[J].Building Construction,2014(11):1 217-1 218.(in Chinese)
汪旭光.爆破手册[M].北京:冶金工业出版社,2010:738. Wang X G.Blasting manual[M].Beijing:Metallurgical Industry Press,2010:738.(in Chinese)
0
浏览量
851
下载量
1
CSCD
关联资源
相关文章
相关作者
相关机构
苏公网安备32010202012147号